MIL-DTL-50647B
samples for first article inspection to those bidders offering a product which has been previously acquired
or tested by the Government, and that bidders offering such products, who wish to rely on such
production or test, must furnish evidence with the bid that prior Government approval is presently
appropriate for the pending contract. Bidders should not submit alternate bids unless specifically
requested to do so in the solicitation.
6.4 Packaging.
6.4.1 Packaging and marking. Packing and marking should be levels A or B as specified by the
contracting activity:
Level A ⎯ In accordance with Drawings 8799620 and 8799621.
Level B ⎯ In accordance with Drawings 8799621 and 9224944.
6.4.2 Lot numbers. Lot numbers should be in accordance with MIL-STD-1168.
6.5 Hazard notice. The cartridge described herein and certain of its components are flammable or
explosive and present hazards in manufacture, handling, storage, and shipment. The contractor should
recognize these properties and take appropriate measures to guard and protect against fire, explosion,
adverse environment, corrosive atmosphere, rough handling, and electrically induced incidents.
6.6 Definitions.
6.6.1 Delay time. Delay time is defined as the time from ignition device impact to the start of pressure
rise.
6.6.2 Time to Pmax. Time to Pmax is defined as the time that elapses between the first indication of
pressure to maximum pressure as recorded on a pressure time record.
6.7 Subject term (keyword) listing.
Ejection systems, aircrew
Emergency escape systems, aircrew
Escape systems, aircrew
Life-saving systems, aircrew
6.8 Changes from previous issue. Marginal notations are not used to identify changes with respect to
the previous issue because of the extensiveness of the changes.